Management and Administration Budget

Over the ten year lifetime of the NDC programme up to a maximum of 10% of the programme budget can be allocated to management and administration costs. 10% of the programme budget for Devonport totals £4,430,000 and the allocation of this budget is set out below - showing actual expenditure to 31st March 2006 and projected expenditure for future years.

2001/2 £ 222,304 Actual
2002/3 £ 414,844 Actual
2003/4 £ 428,516 Actual
2004/5 £ 245,619 Actual
2005/6 £ 443,146 Actual
2006/7 £ 552,779 Actual
2007/8 £ 545,213 Actual
2008/9 £ 557,523 Projected
2009/10 £ 501,237 Projected
2010/11 £ 518,819 Projected
 
Total £ 4,430,000